- 14 - Press Brick work complete 3712.00 Cess Pool 125.00 All lumber and in place - 2017.00 Grounds 90.00 Electric Wiring 600.00 Cement work and plastering 1627.50 Sheet Metal Work and roofing 2000.00 Plumbing Roughing in 400.00 Painting 300.00 All sash glazed 350.00 Nine fire proof windows 90.00 Granolithite floors 125.00 Main Cornice, lookouts and sheathing 40.00 Window frames set in place 474.00 Extra thirty three feet terra cotta floor @ 35.00 11.55 Terra Cotta tile in vault walls 105.00 Granite steps 650.00 Stair work in place rough 75.00 Framing court room cornice 120.00 Cinder Concrete in place 325.00 Bond on contract 124.63 Six front columns ready to stucco 562.00 17,796.68 Less 20% "3,559.33 $14,237.35 $3120.00 4143.48 7,263.48 Amount this estimate 6,973.87 80% of deduction 442.00 Less Estimate # 1 Less Estimate # 2 6,531.87