BAY ST. LOUIS MARINA PROPOSAL "B" COST ESTIMATE
LAUNCHING RAMPS
$ 21,600.00
A.	Four Concrete Ramps
B.	Two Wooden Piers
C.	Lighting
II.	& III. LAND MASS CONSTRUCTION AND CHANNEL DREDGING
270,700.00
IV.
A.	Dredge and Fill
B.	Rip-Rap Shore Protection
C.	Parking Facility
RENOVATION OF FISHING PIER
1,800.00
A.	Water Service
B.	Lighting
V.
VI.
VII.
SEAWARD PARKING LOT
LIGHTING
PEACH SHELTERS
23,000.00
6,600.00
9.300.00
PROJECT COSTS	$343,500-00
CONTINGENCIES	96,500.00
ENGINEERING FEES	35,200.00
STATE ADMINISTRATION	8.800.00
TOTAL PHASE I
$484,000.00